Skip to main content Skip to footer

Milton Farm Battery Storage Project

Introduction

Renewco Power has secured planning permission for Milton Farm Battery Storage Project, a 49.9 MW Battery Energy Storage System (BESS) near Beattock in Dumfries & Galloway.

The planning application was submitted in June 2024 and subsequently considered by Dumfries and Galloway Council's Planning Applications Committee. Following completion of the associated Section 75 Agreement, planning permission was granted for the project.

Milton Farm is now progressing through the next stages of development.

Location

Milton Farm Battery Storage Project is located at Milton Farm, near Beattock in Dumfries & Galloway, approximately 3 km south of Moffat. The site is situated on agricultural land to the east of the A74(M), with access from the local road network.

.

Our Proposal

Milton Farm Battery Storage Project comprises a consented 49.9 MW Battery Energy Storage System (BESS) and associated infrastructure.

The development includes battery storage units, power conversion equipment, electrical infrastructure, a substation and control room, site access and internal roads, security infrastructure and associated drainage and landscaping measures.

The design has been refined through the planning process to respond to the characteristics of the site, including changes to the site access, battery compound and supporting infrastructure.

Planning Permission

Planning permission has been granted by Dumfries and Galloway Council for the 49.9 MW Milton Farm Battery Storage Project.

The application was considered by the Council's Planning Applications Committee, which resolved to approve the development subject to completion of a Section 75 legal agreement. The Section 75 Agreement was subsequently completed and registered, allowing the planning permission to be issued.

The project is now progressing through post-consent development, including detailed design and the discharge of planning conditions. The Planning Decision Notice and key approved plans are available through the Downloads section below.

Indicative Development Timescale

Q1 2023

Site Selection

Q3 - Q4 2023

Preliminary Assessments Site Design and Public Engagement

June 2024

Planning application submitted

November 2024

Planning Committee resolution to appove

2025

Planning permission granted

2025 - 2027

Detailed design and discharge of planning conditions

TBC

Anticipated construction

TBC

Anticipated operation

TBC

Decommissioning

Why is this project needed?

As the UK transitions towards a cleaner electricity system, increasing amounts of electricity are being generated from renewable sources such as wind and solar. Battery energy storage has an important role to play in supporting this transition by helping to balance electricity supply and demand and ensuring that renewable electricity can be used when it is needed.

Milton Farm will be able to import and store electricity from the network when supply is available and export stored electricity at times of higher demand. This flexibility will help support the integration of renewable generation and contribute towards a secure and resilient electricity system.

The 49.9 MW Milton Farm Battery Storage Project could provide up to 199.6 MWh of energy storage, equivalent to approximately four hours of operation at full power. On an illustrative household energy-use basis, a fully charged facility could store enough electricity to meet the daily electricity needs of around 20,000 homes or provide power equivalent to the instantaneous demand of more than 60,000 homes.

 

Project update and contacts

Following the grant of planning permission, Renewco Power is progressing the Milton Farm Battery Storage Project through the next stages of development, including detailed design and the discharge of planning conditions. Further updates will be provided on this website as the project progresses towards construction.

If you have any questions about the Milton Farm Battery Storage Project, please contact us using the ‘Contact Us’ form at the bottom of this webpage or email steven.livingston@cavendishconsulting.com.

Frequently Asked Questions

Battery storage systems can import and store electricity from the National Grid and dispatch this stored electricity as needed to balance the network. This is particularly complementary to renewable energy sources such as solar and wind, which generate intermittent power based upon local weather conditions. Battery storage systems allow this energy to be stored for use in times of higher demand.

During construction, there will be temporary increases in traffic associated with deliveries of equipment and materials to the site. The construction period is currently anticipated to last approximately six months.

Measures will be put in place to manage construction traffic and minimise disruption to the local road network. These will include controls on delivery routes and times, together with measures such as wheel washing and dust management where required.

Construction traffic will be managed in accordance with the requirements of the planning permission and an approved Construction Traffic Management Plan (CTMP).

Planning permission for the Milton Farm Battery Storage Project limits the operational lifetime of the development to a maximum of 40 years. At the end of the operational period, the battery storage facility and associated infrastructure will be fully decommissioned and removed from the site.

The site will then be restored in accordance with the requirements of the planning permission, with the land reinstated to its previous agricultural use. Details of the decommissioning and restoration works will be agreed with Dumfries and Galloway Council through a Decommissioning and Restoration Plan.

Battery storage equipment, including batteries, inverters and transformers, will generate some noise while operating. A detailed Noise Impact Assessment was undertaken as part of the planning application to assess the potential effects on nearby residential properties.

Baseline noise monitoring and detailed acoustic modelling found that predicted operational noise levels from Milton Farm would be below existing representative background noise levels at the nearest residential properties. The assessment therefore concluded that the development would meet the adopted noise criteria by a substantial margin.

The battery storage system is designed to have a very low risk of failure. However, in the unlikely event that a failure should occur, monitoring equipment including fire detection and fire prevention systems will be installed within the containerised battery units to ensure that any fires remain under control. The site access will also be designed to ensure that fire appliances can safely access and egress the site. Renewco Power will continue to monitor industry best practice to ensure that the highest standards of safety are maintained for these units.

Get in touch

We are interested in engaging with wind and solar asset owners, land-owners, developers and funders.

Cookie policy

Learn more about how we use cookies on our website to improve your experience.