Skip to main content Skip to footer

Knocknair Renewable Energy Park

Introduction

Renewco Power has secured planning permission for Knocknair Renewable Energy Park, a solar energy development in Inverclyde, Scotland. The consented project comprises up to 25 MW of solar photovoltaic (PV) generation and associated infrastructure. Planning permission was granted by Inverclyde Council in September 2026.

Location

Knocknair Renewable Energy Park is located on land to the south of Dougliehill Road and east of the B788 in Inverclyde, approximately 1.5 km south-east of Greenock and 0.5 km south of Port Glasgow. The site is situated close to Devol Moor.

Our Proposal

Knocknair Renewable Energy Park comprises a consented solar photovoltaic (PV) development with a generating capacity of up to 25 MW.

The development includes solar PV panels together with associated infrastructure, including a substation, solar PV transformers, security fencing, CCTV, internal access tracks and associated landscaping and environmental mitigation.

The project design was refined through the planning process in response to environmental considerations and consultation, including changes to reduce the development footprint and its landscape and visual effects.

The project received a Gate 2 Phase 1 offer from NESO in January 2025 and Planning permission was granted by Inverclyde Council on 2 September 2026. Further information on the planning permission and approved plans is provided below.

Design Evolution

The Knocknair proposals evolved throughout the design and planning process in response to environmental surveys, consultation and engagement with Inverclyde Council.

The development footprint was refined to respond to peat, ecology, landscape and visual considerations, agricultural land uses and nearby sensitive receptors. The previously proposed battery energy storage system and an additional area of solar panels were removed from the final scheme.

These changes resulted in a smaller, solar-only development that responds more sensitively to the characteristics of the site and its surroundings.

Planning Permission

Planning permission for Knocknair Renewable Energy Park was granted by Inverclyde Council on 2 September 2026. The consent allows for the development of a solar farm with a generating capacity of up to 25 MW, together with associated infrastructure.

During the determination of the application, the proposals were considered by Inverclyde Council’s Planning Committee. Following further consideration of the proposals, including a site visit, the application returned to committee and was approved by a majority of members.

The Council concluded that the proposals comply with the relevant provisions of the Development Plan. The permission is subject to planning conditions designed to ensure that environmental, landscape, ecological, transport and other potential effects are appropriately managed as the project progresses.

The Decision Notice and approved plans are available through the Downloads section below.

Knocknair Renewable Energy Park has secured Gate 2 Phase 1 status under the reformed electricity connection process. This provides a clearer route towards an earlier grid connection, with the detailed connection offer expected in late 2026. Gate 2 status reflects the project’s progress in securing planning permission and advancing towards delivery. The current grid position is for the consented 25 MW solar-only development.

Indicative Development Timescale

Summer 2024

Site Selection

Summer 2024 - 2025

Environmental Assessment and site design

May 2025

First public consultation

June 2025

Second public consultation

August 2025

Planning application submitted

September 2026

Planning permission granted

Late 2026

Detailed Gate 2 connection offer expected

2027 to early 2029

Detailed design, discharge of planning conditions and pre-construction activities

Q2 2029

Anticipated start of construction

Late 2029/early 2030

Anticipated grid connection and operation

Why is this project needed?

The Scottish Government has set a target for Scotland to achieve Net Zero greenhouse gas emissions by 2045 and the UK government have set significant Net zero targets for 2030. Significant additional renewable electricity generation will be required to support the decarbonisation of the UK energy system.

Knocknair Renewable Energy Park will contribute towards these targets by delivering up to 25 MW of additional solar generation. The project will generate renewable electricity while supporting the transition towards a cleaner and more secure energy system.

The development also supports Scotland's wider planning policy objectives to encourage and facilitate renewable energy development.

Public engagement activities

Public consultation events for Knocknair Renewable Energy Park were held in May and June 2025. Feedback received through consultation and engagement was considered as the design developed and helped inform the final proposals.

Renewco Power continued to engage with neighbouring residents, community organisations, local businesses and elected representatives throughout the planning process. This included providing project updates and additional information as the proposals were refined.

The planning consultation attracted 31 representations in support of the project and five objections.

Frequently Asked Questions

Solar technologies capture solar rays from the sun and turn it into useful forms of energy. Photovoltaic (PV) panels comprise several PV cells (which typically produce 1-2 watts of power each) with a whole panel typically producing 250-700 watts depending on the make and model. These PV cells are made of different semiconductor materials, such as silicone, and are sandwiched between protective materials in a combination of glass and / or plastics. When a photon of light from the sun strikes the semiconductor material, it displaces charged particles known as electrons and creates an electrical current. This Direct Current (DC) electricity is then able to be extracted via conductive metal contacts and converted to Alternating Current (AC) electricity via inverters for transmission via the electricity network.

The construction traffic will adhere to an agreed Traffic Management Plan with the council, which will include the use of an existing built access track to avoid impacting local residents. The construction period is expected to take approximately 12 months, and during this time there will be deliveries of equipment to the site. However, the construction period which generates the most traffic is only expected to last 6 months. To manage any potential impacts, Renewco Power and Wardell Armstrong have put in place measures to control construction traffic and minimise disruption to local roads

If consented, the Knocknair Renewable Energy Park project will be subject to a planning condition restricting the total length of the operational period to a maximum of 40 years. At the end of this period, the project will be required to be fully decommissioned, and the land reinstated to its pre-existing condition as agricultural land to the satisfaction of the Local Planning Authority. The details of these decommissioning activities will be secured via a Decommissioning Plan to be submitted for the Council’s approval before the end of the project’s lifespan. It is considered that grazing will continue during the operational period.

A desktop Noise Impact Assessment has been carried out and a report submitted as part of the planning application. Therefore, any operational noise from the project would be low and would comply with all proposed noise limits during all periods of the day and night.

 

The battery storage system is designed to have a very low risk of failure. However, in the unlikely event that a failure should occur, monitoring equipment including fire detection and fire prevention systems will be installed within the containerised battery units to ensure that any emergency remains under control. The site access will also be designed to ensure that fire appliances can safely access and egress the site. Renewco Power are consulting with the Fire and Rescue Service as part of the design and are continuing to monitor industry best practice to ensure that the highest standards of safety are maintained for these units.

Get in touch

We are interested in engaging with wind and solar asset owners, land-owners, developers and funders.

Cookie policy

Learn more about how we use cookies on our website to improve your experience.