Solar technologies capture solar rays from the sun and turn it into useful forms of energy. Photovoltaic (PV) panels comprise several PV cells (which typically produce 1-2 watts of power each) with a whole panel typically producing 250-700 watts depending on the make and model. These PV cells are made of different semiconductor materials, such as silicone, and are sandwiched between protective materials in a combination of glass and / or plastics. When a photon of light from the sun strikes the semiconductor material, it displaces charged particles known as electrons and creates an electrical current. This Direct Current (DC) electricity is then able to be extracted via conductive metal contacts and converted to Alternating Current (AC) electricity via inverters for transmission via the electricity network.
Introduction
Our Proposal
In December 2024, we submitted an Environmental Impact Assessment (EIA) Screening request to Inverclyde Council to help identify key environmental considerations that consultees would like addressed in any future application for Knocknair Renewable Energy Park.
Building on this, we recently submitted a Proposal of Application Notice (PoAN) to Inverclyde Council. This marked the start of the statutory 12-week pre-application consultation phase, ensuring meaningful engagement with the community and stakeholders as the project develops.
Preliminary feasibility work at Knocknair is already underway. So far, we have developed an initial layout featuring approximately 700 solar frames and a Battery Energy Storage System (BESS). As the project progresses, the design will continue to evolve, shaped by consultation feedback and detailed environmental assessments. The following documents will be submitted as part of the planning application:
- Landscape and Visual Impact Assessment;
- Noise Impact Assessment;
- Archaeology & Heritage Impact Assessment;
- Water Environment Appraisal;
- Private Water Supply Risk Assessment;
- Flood Risk Assessment;
- Surface Water Management Plan;
- Peat Technical Note;
- Glint & Glare Assessment;
- Ecological Impact Assessment;
- Outline Construction Environmental Management Plan;
- Transport Statement; and
- Construction Traffic Management Plan.
Indicative Development Timescale
Summer 2024
Site Selection
Summer 2024 - 2025
Environmental Assessment and site design
May 2025
First public consultation
June 2025
Second public consultation
Autumn 2025
Planning application submitted
2030
Construction
2031
Grid connection and operation
Why is this project needed?
The Scottish Government has set targets to reduce Scotland’s emissions of all greenhouse gases to net zero by 2045 at the latest. Significant additional renewable energy capacity, over and above what is produced today, will be needed to facilitate the decarbonisation of transport and heating as Scotland transitions to net zero. The latest National Planning Framework explicitly aims to ‘encourage, promote and facilitate all forms of renewable energy development,’ including solar arrays and battery storage.
Public engagement activities
The Exhibition boards are available for you to download from the 'Downloads' section below on this website.
Get In touch
If you would like to get in touch with us in relation to the Knocknair Renewable Energy Park, please email: knocknair@renewcopower.com
Frequently Asked Questions
Get in touch
We are interested in engaging with wind and solar asset owners, land-owners, developers and funders.