Introduction
Clyde South Energy Park Limited, a fully owned subsidiary of Glasgow-based renewable energy developer Renewco Power Limited, is advancing plans for a new renewable energy project at a site located southeast of Elvanfoot. The project is called Clyde South Energy Park and will include up to 9 wind turbines, up to 180m in height to tip, a battery energy storage system (BESS) and potential for ground mounted solar panels. The project will target commencing operation as the adjacent Clyde Wind Farm is decommissioned at the end of its operational life (currently assumed to be from approximately 2036 onwards).
A request for an Environmental Impact Assessment (EIA) Scoping Opinion from Scottish Minsters has been submitted. This seeks a view from Scottish Ministers, with input from relevant authorities, on which environmental issues should be addressed in the EIA which will guide the ongoing development of the project. The findings of the EIA will be reported in an EIA Report which will form part of the Section 36 application for development consent. The EIA process ensures key environmental factors which must be considered during the planning process are identified and creates opportunities to avoid or mitigate potentially significant environmental effects through the design of the project where possible. The EIA Scoping Request can be downloaded below or accessed on the Energy Consents Unit website
Renewco Power is committed to effective consultation with the local community and will be hosting a number of consultation events seeking feedback on the emerging project details in the coming months.
Why is this project needed?
The Climate Change (Emissions Reduction Targets) (Scotland) Act 2019, which amends the Climate Change (Scotland) Act 2009, sets targets to reduce Scotland’s emissions of all greenhouse gases to net zero by 2045 at the latest. Significant additional renewable energy capacity, over and above what is produced today, will be needed to facilitate the decarbonisation of transport and heating as Scotland transitions to net zero.
Based on the Scoping Layout, the wind farm element of the Watchman Energy Park would be sufficient to power approximately 66,554 homes and will have a significant role in helping the Scottish and UK Governments to meet their emissions reduction and net zero commitments. The solar and BESS will also help balance electricity supply and demand on the National Grid.
.
Location
The Clyde South Energy Park site (the Site) covers an area of approximately 1,059 hectares (ha). The Site is located southeast of Elvanfoot and immediately south of the M74 Motorway and West Coast Main Railway Line within the Lowther Hills. The Site is within the administrative boundary of South Lanarkshire Council.
Why here?
This Site has been selected because:
· It is located close to a concentration of infrastructure along the M74 corridor, providing access for both normal construction traffic and abnormal loads
· it includes the sites of the consented Lion Hill and Crookedstane wind farms (demonstrating the suitability of the Site for wind energy projects)
· it can accommodate a renewable energy development whilst avoiding significant direct effects on areas designated for nature conservation
· there is scope to deliver a suitable access to the Site for both construction traffic and abnormal indivisible loads (AIL) whilst avoiding potential for impacts on local road users
· the character of the landscape in and around the Site can accommodate large modern, commercial wind turbines
Scoping Layout
Several actions have been undertaken to establish the EIA Scoping layout for Clyde South Energy Park. Surveys and site-specific studies that have informed this layout include landscape and visual appraisal, phase 1 peat probing, and ornithological and ecological surveys.
At the current Scoping stage of the project it is assumed the Proposed Development will include:
· 9 wind turbines up to 180 m in height to blade tip
· Battery Energy Storage System (BESS), (approximately 50 MW capacity)
· Ground mounted solar panels
· Onsite substation co-located with the BESS
· Construction compound, laydown areas and borrow pits
· Vehicular access from the public road network (route to be confirmed)
· Habitat management and enhancement
The locations of the solar panels, substation and BESS are currently under detailed consideration, as is the access route, and these will be available for comment later in the pre-application process. Similarly, the positions of the construction compound, laydown areas and borrow pits, alongside internal site access tracks, will be developed as the turbine layout approaches finalisation and in response to further site surveys.
Public Consultation
The first public consultation event for Clyde South will take place on the 1st of December from 3-7 pm at the following location:
Crawford Village Hall,100 Carlisle Road, Crawford, Biggar, ML12 6TW
The event will welcome the local community to speak directly to the project team. However, feedback on the project, and on the community benefit offer, can also be provided online. Further details, including the materials to be presented at the public consultation event, will be published here on the date of the consultation event.
Community Benefit
The Clyde South project will provide a range of benefits for the local community, including a fund which will deliver direct investment into community projects and initiatives. The fund will reflect Scottish Government best practice guidance and will provide a minimum of £5,000 per MW of installed capacity of wind energy. To support engagement on community benefits, a Small Projects community benefit fund of £5,000 will also been launched to support the use of the AssetFace platform. The Small Projects fund will offer grants of up to £500 and will be available to support community-led initiatives in the area. Further details will be published here shortly.
Indicative Development Timescale
October 2025
EIA Scoping Request submission
1st December 2025
Public Consultation Exhibition 1
Q2 2026
Public Consultation Exhibition 2
Q1 2026
EIA Scoping Opinion received
Q3 2026
Submission of S36 application, including EIA Report
Q3 2026
Consent Granted
Q3 2027 - 2035
Discharge of planning conditions
Circa 2035
Start of construction
Circa 2036
Start of operation
40 years from start of operation (circa 2076)
Start of decommissioning
41 years from start of operation (circa 2077)
End of decommissioning
Ongoing design process
Some key next steps to prepare for a Section 36 consent application submission are:
· Address comments submitted as part of the public consultation process;
· Carry out further environmental surveys, including more detailed peat surveys;
· Further develop the turbine layout in response to consultee feedback and environmental sensitivities including:
o key views from surrounding settlements, landmark hills and transport corridors;
o the settings of designated cultural heritage assets in the surrounding area;
o the findings of detailed noise modelling;
o water supply sources;
o sensitive ecological habitats;
o watercourses and associated fisheries, riverine mammals and invertebrates; and both breeding and non-breeding birds, including consideration of disturbance and collision risk.
· Finalisation of development proposed including design of track infrastructure layout, selection of borrow pit search areas, confirmation of solar, substation and BESS locations, confirmation of access routes and identification of suitable construction compound locations;
· Detailed assessment of the impact of the final layout of the development on environmental receptors which will be reported in an EIA Report
Downloads
Get in touch
We are interested in engaging with wind and solar asset owners, land-owners, developers and funders.